Heavy equipment arrived onsite and site work began in the expansion area. The asphalt and the curbs were broken out and removed. The process of removing the undocumented fill and replacing it with document fill commenced. Additionally, the demolition of the concrete in front of the former Target loading dock was completed.


Installation of the drywall and Durock was completed throughout the hallway and each of the restrooms. The ceiling grid installation was completed and the new lights were installed in the hallway. Additionally, ceiling wiring began and an initial coat of paint was put on the hallway walls.