Inside of the expansion area, construction of the new common area bulkheads and framing of the common area ceiling elements commenced this month. Under slab utility work also began throughout the box.
Prep work began ahead of the installation of the new skylights.
Installation of the fixtures for the new additonal restrooms commenced this month.
Removal and Installation of the new tile in the realignment area has begun.