The photo below was taken from inside Autobahn. This month, storefront work and track installation were completed. Additionally, karts were loaded into the space and assembled.
The photo below was taken from outside the Kraze Burger space. This month, Kraze Burger began their construction.
The photo below was taken from inside the Uptown Alley. This month, the new slab was poured. and contractors continued the process of running the overhead conduits and framing.
The photo below was taken from outside Entrance 1. The contractors began pouring the curbs for the new parking lot islands this month.
The photo below was taken from inside the expansion electrical room. NOVEC began the process of connecting permanent power to the expansion this month.