The photos below were taken from outside Entrance 1 & Entrance 6. The installation of interior doors completed on both entrances and the installation of exterior doors commenced this month. Additionally, framing continued on both entrances.
![IMG_1408](https://www.manassasmall.com/wp-content/uploads/sites/6/2016/09/IMG_1408.jpg)
![IMG_1416](https://www.manassasmall.com/wp-content/uploads/sites/6/2016/09/IMG_1416.jpg)
The photo below was taken from inside the expansion electrical room. NOVEC completed the process of connecting permanent power to the expansion this month.
![IMG_1074](https://www.manassasmall.com/wp-content/uploads/sites/6/2016/09/IMG_1074.jpg)
The photo below was taken from inside Autobahn. Charging stations, guard rails, storefront signage and exterior signage were installed this month.
![IMG_1295](https://www.manassasmall.com/wp-content/uploads/sites/6/2016/09/IMG_1295.jpg)
![IMG_1298](https://www.manassasmall.com/wp-content/uploads/sites/6/2016/09/IMG_1298.jpg)
The photo below was taken from outside the Kraze Burger space. This month, Kraze Burger began their framing, duct work and electrical work.
![IMG_1286](https://www.manassasmall.com/wp-content/uploads/sites/6/2016/09/IMG_1286.jpg)
The photo below was taken from inside Uptown Alley. This month, framing continued and duct work began.
![IMG_1291](https://www.manassasmall.com/wp-content/uploads/sites/6/2016/09/IMG_1291.jpg)