The photos below were taken from outside Entrance 1 & Entrance 6. The installation of interior doors completed on both entrances and the installation of exterior doors commenced this month. Additionally, framing continued on both entrances.
The photo below was taken from inside the expansion electrical room. NOVEC completed the process of connecting permanent power to the expansion this month.
The photo below was taken from inside Autobahn. Charging stations, guard rails, storefront signage and exterior signage were installed this month.
The photo below was taken from outside the Kraze Burger space. This month, Kraze Burger began their framing, duct work and electrical work.
The photo below was taken from inside Uptown Alley. This month, framing continued and duct work began.